Case study • Open permits • Homestead • Closed 2024

A 2022 permit, left open by the original contractor, closed in six weeks.

The permit had been pulled in 2022 for an impact-window installation. The work was completed. The final inspection was never scheduled. Two years later, a refinance underwriter caught it.

Situation

The homeowner had replaced eleven windows in 2022 with impact-rated units under a permit pulled by the installing contractor. The installation was completed within weeks. The contractor walked away without closing the permit — likely an oversight, possibly because the contractor went out of business shortly afterward.

In 2024, the homeowner applied for a cash-out refinance. The lender’s title check pulled the property record and flagged the open permit. The underwriter required the permit be finaled before funding. The homeowner had a closing deadline 8 weeks out.

Challenges
01

The original contractor was no longer in business.

There was no contractor to schedule the inspection or address any failed conditions.

02

Product approval documentation was incomplete.

The homeowner had product approval sheets for some windows but not all. We had to reconstruct the package.

03

The closing deadline was tight.

Standard Building Department inspection lead times in Homestead can run 2–3 weeks. A failed inspection would require a re-inspection cycle. Margin was thin.

Resolution

Document flow:

  1. Day 1
    Property record pull, open permit file reviewed
  2. Day 2
    Homeowner provided existing product approval sheets; gaps identified
  3. Day 5
    Florida Building Code NOAs for two missing window models obtained and added to file
  4. Day 9
    Inspection request submitted directly to Homestead Building Department
  5. Day 14
    Final inspection scheduled (day 21)
  6. Day 21
    Final inspection — specialist on site; inspector noted one missing flashing detail on a single window
  7. Day 24
    Flashing detail corrected by an installer in our network
  8. Day 29
    Re-inspection — passed
  9. Day 31
    Permit finaled; closed permit document issued to homeowner
  10. Day 35
    Refinance underwriter received closed permit; funding proceeded
  11. Day 42
    Refinance closed
Outcome
Permit status Closed and finaled
Refinance Funded; closed 6 days early relative to original deadline
Property record Window installation permitted, finaled, recorded
Total engagement 6 weeks
Property owner
“Refinance underwriter caught it. Our installer was gone — no one to call. Permit Solutions pulled the record the day we called, scheduled the inspection, fixed one flashing detail, and finaled the permit in six weeks. Refinance closed on time.”
Homeowner • Case facts authorized for publication
Open permit holding up your transaction?

Tell us the address. We’ll pull the record.

Share your address and closing date if you have one. A specialist returns the assessment within one business day — usually same day.

Call 305-600-9422 Request Review